Quantcast

Indy Standard

Friday, September 20, 2024

Phase 1: 75th Street Sidewalk Schedule and 7/15/22 Update

Phase 1: 75th Street Sidewalk Schedule and 7/15/22 Update

Calumet is providing materials, services and installation of the Phase 1: 75th Street Sidewalk Project. Contractually, Calumet will be working on this project May 30th through July 31st. Crossroad Engineers will be providing bi-weekly summaries of work progress, a look ahead of what Calumet will be doing for the upcoming 2 weeks, and tracking work days and weather days throughout the project. Also, our July 11 Town Meeting will be providing a progress update.

July 15, 2022 Update:

From CrossRoad Engineers: Prior to July 11, construction was on hold due to an ongoing delay for an unmarked fiber optics line. Construction commenced on July 11. Two storm drain structures and 120ft storm pipe were installed. In addition, sidewalk prep began between Illinois St. and Meridian St. This included clearing of Right of Way and grading.

Thank you,

Colleen Field

Meridian Hills Town Councilor

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS